Permit revisions.

We deal with multiple jurisdictions, and they are all different. For revisions after the plans are approved and/or issued most want just the revised plan sets. All jurisdictions have this in common: clouds/deltas and detailed responses or narratives of the changes must be provided, and all plans must be signed and stamped the same as they were for the original submittal.
 
We require the revised plans with a narrative on the changes to be submitted as a plan check. We charge review fees.
 
There is a "permit revisions form" that we use and ask the applicant to submit with the changes; if it is a big review and a lot of time is spent reviewing, I would charge an additional fee/fees as appropriate. Once the revisions are approved, the plans get re-issued.
 